aboutsummaryrefslogtreecommitdiffstats
path: root/docs/RELEASE-PROCEDURE
blob: fc31274e82d6c433a8788a7717a52fe3e39211c9 (plain)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
curl release procedure - how to do a release
============================================

in the source code repo
-----------------------

- edit `RELEASE-NOTES` to be accurate

- update `docs/THANKS`

- make sure all relevant changes are committed on the master branch

- tag the git repo in this style: `git tag -a curl-7_34_0`. -a annotates the
  tag and we use underscores instead of dots in the version number. 
   
- run "./maketgz 7.34.0" to build the release tarballs. It is important that
  you run this on a machine with the correct set of autotools etc installed
  as this is what then will be shipped and used by most users on *nix like
  systems.

- push the git commits and the new tag

- gpg sign the 4 tarballs as maketgz suggests

- upload the 8 resulting files to the primary download directory

in the curl-www repo
--------------------

- edit `Makefile` (version number and date),

- edit `_newslog.html` (announce the new release) and

- edit `_changes.html` (insert changes+bugfixes from RELEASE-NOTES)

- commit all local changes

- tag the repo with the same tag as used for the source repo

- make sure all relevant changes are committed and pushed on the master branch

  (the web site then updates its contents automatically)

inform
------

- send an email to curl-users, curl-announce and curl-library. Insert the
  RELEASE-NOTES into the mail.

celebrate
---------

- suitable beverage intake is encouraged for the festivities

curl release scheduling
=======================

Basics
------

We do releases every 8 weeks on Wednesdays. If critical problems arise, we can
insert releases outside of the schedule or we can move the release date - but
this is very rare.

Each 8 week release cycle is split in two 4-week periods.

- During the first 4 weeks after a release, we allow new features and changes
  to curl and libcurl. If we accept any such changes, we bump the minor number
  used for the next release.

- During the second 4-week period we do not merge any features or changes, we
  then only focus on fixing bugs and polishing things to make a solid coming
  release.

Coming dates
------------

Based on the description above, here are some planned release dates (at the
time of this writing):

- June 17, 2015 (version 7.43.0)
- August 12, 2015
- October 7, 2015
- December 2, 2015
- January 27, 2016
- March 23, 2016
- May 18, 2016
- July 13, 2016
- September 7, 2016